Braemar VRF GMV5 / MCMX – Commissioning & Re‑Commissioning Checklist

Post Installation, PCB Replacement & System Configuration Changes


This article defines the mandatory commissioning and re‑commissioning process for:

  • Braemar VRF GMV5 / MCMX systems
  • New system installations
  • System expansions or reconfiguration
  • Replacement of:
    • Outdoor unit main PCB
    • Compressor drive board
    • Fan drive board
    • Indoor unit PCBs

Why This Checklist Is Critical

Failure to complete commissioning correctly will guarantee repeat faults, most commonly:

  • C5 – IDU Project Code Conflict
  • C6 – ODU Quantity Inconsistency
  • CC / CF / CJ – Master & addressing errors
  • U0 – Insufficient compressor preheating
  • U2 – Capacity code / DIP switch error
  • U4 – Lack of refrigerant protection

Commissioning is NOT optional after PCB replacement or any system layout change.


Primary Reference Manuals (With Page Numbers)

ManualPurposePages
GMV5 / MCMX Outdoor Unit Service Manual (MCMX‑03‑B)Commissioning & debugging procedurepp. 10–13
GMV5 / MCMX Outdoor Unit Service Manual (MCMX‑03‑B)Electrical & wiring requirementspp. 14–17
Braemar VRF Flowcharts Manual (VRFODU‑PT1‑03‑B)Fault confirmation if commissioning failsSections C & U, pp. 10–20 & 63–64

When Commissioning MUST Be Performed

Commissioning or re‑commissioning is mandatory when:

  • New VRF system installation is completed
  • Outdoor unit main PCB is replaced
  • Compressor or fan drive PCB is replaced
  • Indoor unit PCB is replaced
  • Indoor units are added or removed
  • Outdoor units are added or removed
  • Communication wiring is modified
  • DIP switch settings are changed

MCMX‑03‑B – Commissioning overview, pp. 10–13


Pre‑Commissioning Checklist (Before Power‑On)

1. Electrical & Wiring Verification

Confirm before energising the system:

  • Correct mains voltage present at ODU
  • Voltage within allowable limits under load
  • All indoor & outdoor units powered
  • Verified earth continuity
  • Communication wiring (D1 / D2) daisy‑chained correctly
  • Shield earth connected at ODU only
  • Matched resistor installed at final indoor unit

MCMX‑03‑B – Electrical Part: pp. 14–17


2. Refrigerant & Piping Checks

  • Pipework pressure‑tested
  • System evacuated fully
  • Refrigerant charge added per total pipe length
  • Gas and liquid service valves fully open
  • No refrigerant leaks detected

MCMX‑03‑B – Refrigeration & charging references, pp. 8–9 & 10–11


3. DIP Switch & Hardware Configuration

  • One (and only one) Master Outdoor Unit selected (SA8)
  • All other ODUs set as slave
  • Capacity DIP switches correctly set for model
  • Emergency operation DIP switches disabled

VRF Flowcharts Manual:

  • Master/DIP logic – Section C, pp. 17–19
  • Capacity/DIP validation – Section U, p. 63

Mandatory Compressor Pre‑Heating

Critical Requirement – Do NOT Skip

  • ODU must be powered continuously for a minimum of 8 hours
  • Allows compressor crankcase heater to stabilise oil temperature

Failure results in:

  • U0 – Insufficient Compressor Preheat
  • High risk of compressor damage

MCMX‑03‑B – Debugging & preheat confirmation: pp. 12–13


Commissioning Procedure (Outdoor Unit Debug Mode)

MCMX‑03‑B – Test Operation & Debugging: pp. 10–13


Step 1 – Enter Debug / Commissioning Mode

  • Access outdoor unit PCB
  • Press & hold SW7 (Commissioning Button) as specified
  • Confirm system enters debug sequence

Step 2 – Address Allocation

  • System automatically allocates:
    • ODU addresses
    • IDU addresses
  • Confirm indoor unit count matches installed units

Incorrect count will later trigger:

  • C4
  • C5
  • C6

Step 3 – Outdoor Unit Quantity Confirmation

  • System confirms number of connected ODUs
  • Any mismatch triggers C6

Correct wiring or power issues before proceeding


Step 4 – Indoor Unit Quantity Confirmation

  • Confirm detected IDU quantity
  • Manually correct if prompted

Common faults if skipped:

  • C4 – IDU Missing
  • C5 – Project Code Conflict

Step 5 – Capacity Ratio Validation

System checks IDU vs ODU capacity:

ConditionFault Code
IDU capacity >135%CH
IDU capacity <50%CL

VRF Flowcharts Manual – Capacity logic: pp. 18–20


Step 6 – Outdoor Component Self‑Check

System evaluates:

  • Compressor
  • Outdoor fans
  • Sensors
  • Drive boards

Any detected fault must be cleared before proceeding.


Step 7 – Indoor Component Self‑Check

System checks:

  • Indoor fan operation
  • Sensors
  • Drain components

VRF Flowcharts Manual – Indoor checks: pp. 47–50


Step 8 – Refrigerant & Valve Confirmation

System verifies:

  • Refrigerant pressure relationship
  • Valve position

Faults here include:

  • U4 – Lack of Refrigerant
  • U6 – Valve abnormality

VRF Flowcharts Manual – Section U: pp. 63–64


Step 9 – Commissioning Operation Run

  • System runs in:
    • Cooling or
    • Heating (ambient dependent)
  • Monitor minimum 20 minutes stable operation

Step 10 – Commissioning Complete

  • System exits debug mode
  • Returns to standby
  • No active fault codes present

Commissioning successful


Re‑Commissioning After PCB Replacement

When any PCB is replaced, stored commissioning data is lost.

Always perform:

  • Full commissioning cycle
  • Do not skip steps
  • Do not attempt partial commissioning

Skipping recommissioning most commonly leads to:

  • C5 / C6
  • CC / CF
  • U0 / U2 / U4

MCMX‑03‑B – PCB replacement & recommissioning notes: pp. 10–13


Final Verification (Before Leaving Site)

Confirm:

  • No active fault codes
  • Indoor units respond correctly
  • System heats/cools as expected
  • Correct indoor unit grouping
  • Stable operation for ≥20 minutes

Key Technician Takeaways

  • Commissioning is a system‑defining process
  • Any skipped step can cause system‑wide faults
  • PCB replacement always requires recommissioning
  • Proper commissioning prevents repeat visits and ongoing issues