TQ / TQR DGH – FC32 & FC45 Combustion Air Pressure Too Low at Start or During Run

⚠️ Safety Notice – Gas Heating Products

This appliance must only be installed, commissioned, serviced and repaired by suitably qualified and licensed personnel.


Before commencing work, complete a task-specific risk assessment and ensure gas and electrical safety requirements, ventilation provisions, safe access, adequate service clearances and appropriate PPE have been considered. All work must comply with applicable regulations, standards and manufacturer requirements.


Particular care must be taken when working around gas systems, electrical components, combustion products, hot surfaces, moving parts, roof spaces, ceiling spaces and confined spaces.


Do not proceed if safe access, required clearances, ventilation requirements, confined space risks or appropriate safety controls cannot be achieved and maintained. 


Safety takes priority over diagnosis, repairs, installation schedules and customer expectations. If the task cannot be completed safely, it must not proceed until the risks have been adequately controlled.


Click link below to view:

TQ / TQM Fault Codes (FC Errors) + ICS LED Flash Guide – Diagnostics & Quick Checks: Seeley International Pty Ltd


Fault Description

FC32 – Combustion Air Pressure Too Low at Start

The heater was unable to achieve the required combustion suction pressure during the startup sequence. 

FC45 – Combustion Air Pressure Too Low During Run

The heater initially started correctly but lost combustion suction pressure during operation.

These faults are commonly caused by:

  • Incorrect flue installation.
  • Incorrect flue terminal/cowl selection.
  • Excessive flue length or bends.
  • Wind affecting the flue terminal.
  • Restrictions in the flue system.
  • Condensation or blockages in pressure sensing hoses.
  • Air leaks in the combustion pressure sensing system.

Before replacing components, the complete flue system should be checked against the installation requirements.


Step 1 – Verify Combustion Pressure Testing Method

Before carrying out any pressure checks, ensure the manometer is connected correctly.


For TQR5/TQM5 and TQR6/TQM6 modulating heaters, combustion pressure must be measured using a T-piece fitted into the black combustion pressure sensing hose, not by connecting directly to the combustion fan pressure spigot.

Why This Is Important

The heater controls combustion fan speed using feedback from the pressure sensor. If the pressure sensor is disconnected during testing, the heater will continue increasing fan speed in an attempt to achieve the target pressure.

This can result in:

  • Incorrect pressure readings.
  • Misdiagnosis of the fault.
  • Pressure values that do not represent normal heater operation.

Correct Testing Method

✅ Leave the pressure sensing system connected.

✅ Fit a temporary T-piece into the black suction hose.

✅ Connect the manometer to the T-piece.

✅ Measure the pressure being seen by the heater's pressure sensor.

Incorrect Testing Method

❌ Connecting a manometer directly to the combustion fan pressure spigot.

❌ Disconnecting the pressure sensor hose during testing.

Recommended Parts

The following spare parts can be used to create a temporary test point:

Part NumberDescription
628806T-Piece Pressure Switch Fitting
814803Pressure Switch Tube (5mm ID x 10mm)

These components can be purchased through Spare Parts.


IMPORTANT

When testing a modulating heater, the pressure sensor must remain connected while the manometer is fitted.

If the pressure sensor is removed from the circuit, the combustion fan will continue ramping up in speed while trying to achieve the target pressure. Because the heater is no longer receiving pressure feedback, it will never know it has achieved the correct pressure, resulting in misleading readings.

Using a T-piece allows both the pressure sensor and the manometer to remain connected, ensuring the pressure being measured accurately reflects normal heater operation.


Combustion Pressure Guide (Pa)

Heater Model25%50%75%100%
DEFAULT 5M85135210290
DEFAULT 6M88120195320
TQM 516 N74110175275
TQM 520 X N85135210290
TQM 530 X N85115205290
TQS 420 X N85135210290
TQS 430 X N7090145250
TQMD 516 N74110175275
TQMD 520 N85135210290
TQMD 530 N85115205290
SSQ 520 X N85115205290
SSQ 530 X N85115205290
TQM 18.6 N7580160300
TQM 623 X N8595188320
TQM 630 X N8595195310
TQS 523 X N8595188320
TQS 530 X N6575150260
TQS 623 X N85120175260
TQS 632 X N60100200330
TQS 720 N4992155305
TQS 730 N4992155305
TQM 520X U100185280340
TQM 530X U80120240360
TQM 623X U80110180260
TQM 630X U100140200260
TQM 520X P / TQMD 520XP86142262335
TQM 530X P / TQMD 530XP80128215360
TQM 6X23 P7096160235
TQM 6X30 P95130200310
TQA 530X N85115205290
TQA 632X N8595195310

Notes

  • These values are a guide only and should be measured using a T-piece installed in the combustion pressure sensing hose as described in Step 1.
  • The pressure sensor must remain connected during testing on modulating heaters.
  • Readings significantly below the expected value at any gas rate typically indicate a flue restriction, incorrect flue configuration, air leak, blocked pressure sensing hose, moisture contamination, combustion fan issue, or adverse wind effects.

Step 2 – Confirm the Correct Flue Terminal Has Been Fitted

Incorrect flue terminals can increase resistance and make the installation more susceptible to wind-related pressure faults.

TQR5 / TQM5 Modulating Non-Condensing Heaters

External / Underfloor Installations

Flue Terminal P/N 641706.

Internal Installations

100mm AGA Approved Flue System with 100mm AGA Approved Cowl.


TQR6 / TQM6 Modulating Condensing Heaters

Internal Installations

Flue Terminal P/N 641713.

External / Underfloor Installations

Flue Terminal P/N 641607.


Adaptor Flue Terminal P/N 641748.



Step 3 – Check Flue Length and Number of Bends

TQR5 / TQM5 Modulating Non-Condensing Heaters

The installation manual specifies:

Maximum Flue Lengths

  • Maximum vertical flue length: 4.8m
  • Maximum horizontal flue length: 4m
  • Maximum combined flue length: 6m

Maximum Bends

  • Maximum 2 x 90° bends
  • Two 45° bends are equivalent to one 90° bend

Flue Requirements

  • Heater must be flued using 100mm AGA approved metal flue pipe.
  • External socket joins must face downward.
  • Internal socket joins must face upward.
  • Flue joins must be adequately sealed.
  • Twin-wall metal flue must be used where the flue is not readily accessible.
  • Twin-wall metal flue is recommended on flue runs exceeding 2m.

Common Installation Issues

❌ Flue length exceeds maximum allowable limits.

❌ More than 2 × 90° bends installed.

❌ Additional bends added after commissioning.

❌ Incorrect flue pipe diameter used.

❌ Incorrect terminal/cowl fitted.

❌ Terminal location affected by wind turbulence.

❌ Partial blockage within the flue system.


TQR6 / TQM6 Modulating Condensing Heaters

The installation manual specifies:

Maximum Flue Lengths

  • Maximum vertical rise: 5m
  • Maximum total flue length: 12m

Maximum Bends

  • Maximum 4 x 90° bends
  • Two 45° bends are equivalent to one 90° bend

Flue Pipe Requirements

  • Must be installed using 100mm DWV plastic pipe and fittings compliant with AS1260.
  • Flue system must terminate using a 100mm DWV vent cowl.
  • The flue terminal on the heater is designed to accept either:
    • The male end of a 100mm DWV M-F elbow, or
    • 100mm DWV pipe.

Flue Joint Requirements

All flue and condensate drain joints must be sealed using:

  • Silicone sealant, or
  • PVC solvent cement and primer.

Common Installation Issues

❌ Flue length exceeds the maximum allowable limits

❌ More than 4 × 90° bends installed

❌ Incorrect flue pipe size used

❌ Incorrect flue terminal or components used

❌ Flue terminal location affected by wind

❌ Partial blockage within the flue system

❌ Condensate drain installed incorrectly

❌ Moisture in the pressure sensing hose

❌ Pressure sensing hose contacting cold surfaces

The service manual specifically notes that the suction hose should not rest against the heater lid or panels where condensation can form and partially block the pressure signal.


Step 4 – Inspect the Complete Flue System


Inspect the entire flue system for any restriction to airflow, including insect nests, debris, partial blockages or incorrectly installed flue components.

Even a minor restriction can reduce combustion pressure and result in FC32 or FC45 faults.


Step 5 – Check Flue Terminal Location

Wind effects are one of the most common causes of intermittent FC45 faults.


Check whether the flue terminal is installed in a location susceptible to wind turbulence, such as:

  • Near roof ridges.
  • In roof valleys.
  • Near tall walls.
  • Close to nearby buildings or structures.

FC45 faults that occur mainly during windy conditions often indicate a flue terminal location issue.


Step 6 – Verify Flue Clearances

Minimum clearances from the flue terminal must be maintained.


Confirm the flue terminal complies with the minimum clearances specified in the installation manual.

Incorrect terminal clearances can contribute to wind-related combustion pressure faults in some installations.


Step 7 – Condensing Models Only (TQR6 / TQM6)

Moisture trapped in pressure sensing hoses can reduce the pressure signal seen by the ICS and generate FC32 or FC45 faults.


Step 8 – Inspect the Pressure Sensing System

Check:

  • Pressure sensing hose.
  • Hose joiners.
  • Combustion fan pressure tapping.
  • Pressure sensor connections.

Look for:

  • Kinks.
  • Splits.
  • Cracks.
  • Restrictions.
  • Moisture contamination.

Any restriction between the combustion fan and the pressure sensor can affect the pressure reading seen by the ICS.


Step 9 – Inspect Heater Joins and Combustion Fan Sealing

Particularly on heaters that have been split during installation.

Check:

  • Black joiner between heater halves.
  • Combustion fan O-ring seal.
  • Combustion fan mounting.
  • Combustion fan locking tabs.
  • Combustion fan sealing surfaces.

Look for:

  • Cracks.
  • Air leaks.
  • Poor sealing.
  • Damage to hose joiners.

Air leaks at these locations can reduce combustion suction pressure and generate FC32 or FC45 faults.


Before Replacing Components

Verify the following:

Confirm the flue installation complies with the installation requirements and that no issues have been found with:

  • Flue length.
  • Number of bends.
  • Flue terminal selection.
  • Flue terminal location.
  • Restrictions within the flue system.
  • Condensate drainage (TQR6/TQM6).
  • Pressure sensing hoses and connections.

If all checks are satisfactory and FC32 or FC45 faults persist, further investigation of the combustion fan, pressure sensor or ICS may be required.


Click link below to view: 6.2 Combustion Fan Testing - 24 Vdc Combustion Fan (Modulating)

Braemar TQ Gas Heater Component Testing & Fault Diagnosis TQ Service Guide 2023 (644066M) : Seeley International Pty Ltd






Check the ICS wiring loom plug connection:

Ensure the brown wire (circled below) is securely connected and not causing a poor electrical connection. In some cases, the pin associated with the brown wire may need to be gently pulled through to fully engage, similar to the other pins in the plug.



Ensure the large white plug is making a secure electrical connection, particularly at the pin connected to the brown wire.




image
image
image


Fault code history can be accessed:

SETTINGS/SERVICE/GAS HEATER 01/7378 CONT/FAULT LOG


YouTube Video - MagIQtouch Heater Fault Log 



image